# Whole House Remodel Checklist: A 60-Item Step-by-Step Guide

Whole house remodel checklist with 60 sequential steps from planning to final inspection. Built for Los Angeles homeowners by a CSLB licensed contractor.

May 12, 20268 min readCSLB License #1072368

![whole house remodel checklist](https://www.mycalibuilders.com/blog-images/whole-house-remodel-checklist.jpeg)

Trust and Process project by MY Cali BUILDERS INC

**Short answer.** The 60-item checklist below covers a whole house remodel in Los Angeles from planning to final inspection. The phases run sequentially with overlap during long-lead activities. Skip a step and pay for it later. Built from years of CSLB-licensed remodel projects (#1072368).

## Phase 1: Planning (months 1 to 2)

1. Define the goals of the remodel in one paragraph.
2. Write a prioritized scope document (must-have, want, future).
3. Set the total budget cap and include 15 to 20 percent contingency.
4. Decide whether to stay in the home or move out during construction.
5. Tour 3 to 5 finished remodels at similar scope for reference.
6. Build a visual reference document (50 to 100 images).
7. Decide on design-build vs hire-an-architect path.
8. Identify must-keep elements in the existing home.

## Phase 2: Contractor selection (months 2 to 3)

1. Build a list of 6 to 10 qualified candidates.
2. Run CSLB license lookup on each.
3. Phone screen the top 5 to 6.
4. Schedule onsite meetings with 4 finalists.
5. Request bids from 3 final candidates on identical scope.
6. Compare bids line by line in a spreadsheet.
7. Call 3 references per finalist.
8. Visit one active project per finalist.
9. Negotiate scope, schedule, and contract terms.
10. Have a construction lawyer review the contract over $50,000.
11. Sign the contract and pay the deposit (capped at 10 percent or $1,000).

## Phase 3: Design and selections (months 3 to 5)

1. Schematic floor plans complete.
2. Elevations and 3D renderings complete.
3. Structural review by a licensed engineer (if structural changes).
4. Title 24 energy compliance analysis complete.
5. Cabinetry selected and ordered.
6. Tile selected and ordered (all rooms).
7. Plumbing fixtures selected and ordered.
8. Lighting fixtures selected and ordered.
9. Flooring selected.
10. Paint colors selected.
11. Hardware selected.
12. Appliances ordered.
13. Windows and doors specified and ordered.
14. Final drawings signed off by homeowner.

## Phase 4: Permits and pre-construction (months 4 to 6)

1. Permit application submitted to LADBS.
2. Coastal Commission or HPOZ overlay review (if applicable).
3. Plan check corrections addressed.
4. Permits issued and posted onsite.
5. Insurance certificates (COI) received from contractor and subs.
6. Pre-construction meeting with project manager and trades.
7. Construction start date confirmed.
8. Living arrangements finalized (rental, family, in-place).
9. Storage arranged if needed.
10. Neighbors notified of construction start date.

## Phase 5: Construction (months 6 to 10)

1. Demolition complete.
2. Hidden conditions documented and change orders signed.
3. Foundation work complete (if applicable).
4. Framing complete and inspected.
5. Roofing complete (if applicable).
6. Windows and exterior doors installed.
7. Rough plumbing inspected.
8. Rough electrical inspected.
9. Rough HVAC inspected.
10. Insulation inspected.
11. Drywall complete.
12. Interior trim and casing complete.
13. Painting complete.
14. Tile complete.
15. Cabinetry installed.
16. Countertops templated and installed.
17. Plumbing trim installed.
18. Electrical trim installed.
19. Flooring complete.
20. Final cleaning.

## Phase 6: Closeout (months 10 to 12)

1. Punch list walkthrough complete.
2. All punch list items closed.
3. Final inspection with LADBS passed.
4. Certificate of Occupancy received (if applicable).
5. Warranty documents in hand.
6. Final payment released.
7. Move back in.

For full home remodel services, see [full home remodeling](https://www.mycalibuilders.com/services/full-home-remodeling). For schedule expectations, read [how long does it take to remodel a house](https://www.mycalibuilders.com/blog/how-long-does-it-take-to-remodel-a-house). For mistakes to avoid, see [11 kitchen remodel mistakes](https://www.mycalibuilders.com/blog/kitchen-remodel-mistakes-to-avoid). To start a whole-home conversation, open the [contact page](https://www.mycalibuilders.com/contact-us).

Free onsite estimate

### Ready to start your Full Home Remodeling project?

We come to you, review the scope, and give you a written estimate before any work starts. No pressure. No vague quotes. CA Contractor License #1072368.

[Call us](tel:+13102200903) [Text Us](sms:+13102200903) [Get a free estimate](https://www.mycalibuilders.com/contact-us)

Project gallery

## Real projects from our crew

Recent work from MY Cali Builders across the San Fernando Valley.

[See full gallery](https://www.mycalibuilders.com/gallery)

![Traditional kitchen with wooden cabinets and tiled countertops.](https://www.mycalibuilders.com/project-media/kitchen-remodeling/WhatsApp%20Image%202026-05-08%20at%2008.35.33%20(4).jpeg)

Kitchen Remodeling

![Modern living space with wood paneling and minimalist furniture.](https://www.mycalibuilders.com/project-media/kitchen-remodeling/WhatsApp%20Image%202026-05-08%20at%2008.35.34%20(1).jpeg)

Kitchen Remodeling

![Contemporary kitchen featuring stainless steel appliances and patterned backsplash.](https://www.mycalibuilders.com/project-media/kitchen-remodeling/WhatsApp%20Image%202026-05-08%20at%2008.35.43%20(1).jpeg)

Kitchen Remodeling

Related services

### See how we approach this work

- [Full Home Remodeling](https://www.mycalibuilders.com/services/full-home-remodeling)
- [Full Home Remodeling in San Fernando Valley](https://www.mycalibuilders.com/service-areas/san-fernando-valley/full-home-remodeling)
- [Full Home Remodeling in Calabasas](https://www.mycalibuilders.com/service-areas/calabasas/full-home-remodeling)

About the author

Written by the MY Cali BUILDERS INC team. Licensed California general contractor, CSLB #1072368. Based in Woodland Hills and serving the San Fernando Valley. [About our team](https://www.mycalibuilders.com/about-us).

FAQs

## Frequently asked questions

Start the planning phase 6 to 9 months before desired construction start. Permits and material lead times consume 4 to 6 months of that runway.

A defined and prioritized scope document before any contractor conversations. Without it, bids cannot be compared, scope keeps drifting, and budget gets blown.

Yes. Selections should be 90 percent complete before construction starts. Finalize cabinetry, tile, plumbing fixtures, lighting, paint, flooring, and hardware. Incomplete selections trigger schedule slips during construction.

Weekly site meetings with a written agenda based on the checklist. The contractor's project manager confirms which items are complete, in progress, and blocked. Document each meeting.

15 to 20 percent of contract value for whole-house remodel work. Hidden conditions in older homes (plumbing, electrical, structural) almost always surface during demo. The contingency covers them without delaying the project.

Keep reading

## More from the blog

[![how long does it take to remodel a house](https://www.mycalibuilders.com/blog-images/how-long-does-it-take-to-remodel-a-house.jpeg)](https://www.mycalibuilders.com/blog/how-long-does-it-take-to-remodel-a-house)

Trust and Process6 min read

### [How Long Does It Take to Remodel a House in Los Angeles?](https://www.mycalibuilders.com/blog/how-long-does-it-take-to-remodel-a-house)

Realistic timelines for whole house, kitchen, bathroom, and ADU remodels in Los Angeles. Design, permits, construction, and where projects slip.

May 12, 2026 [Read article](https://www.mycalibuilders.com/blog/how-long-does-it-take-to-remodel-a-house)

[![how to choose general contractor](https://www.mycalibuilders.com/blog-images/how-to-choose-a-general-contractor.jpeg)](https://www.mycalibuilders.com/blog/how-to-choose-a-general-contractor)

Trust and Process8 min read

### [How to Choose a General Contractor in California: A Step-by-Step Screening Process](https://www.mycalibuilders.com/blog/how-to-choose-a-general-contractor)

A practical step-by-step process to choose a general contractor in California. License verification, references, bids, and contract review.

May 12, 2026 [Read article](https://www.mycalibuilders.com/blog/how-to-choose-a-general-contractor)

[![kitchen remodel mistakes to avoid](https://www.mycalibuilders.com/blog-images/kitchen-remodel-mistakes-to-avoid.jpeg)](https://www.mycalibuilders.com/blog/kitchen-remodel-mistakes-to-avoid)

Kitchen Remodeling8 min read

### [11 Common Kitchen Remodel Mistakes to Avoid (From a Licensed LA Contractor)](https://www.mycalibuilders.com/blog/kitchen-remodel-mistakes-to-avoid)

11 kitchen remodel mistakes a licensed Los Angeles contractor sees most often. Layout, lighting, permits, cabinet ordering, and the costliest calls.

May 12, 2026 [Read article](https://www.mycalibuilders.com/blog/kitchen-remodel-mistakes-to-avoid)

[See all articles](https://www.mycalibuilders.com/blog)

Ready to get started?

## Get a free estimate

Free onsite visit. Written estimate. You will see the full scope before you decide. No pressure, no vague quotes.

[Call us](tel:+13102200903) [Text Us](sms:+13102200903) Send us a message

License #1072368. Fully insured. Serving the San Fernando Valley since 2020.