Skip to main content
MY Cali Builders Inc

Kitchen Remodel Timeline: Week-by-Week Schedule for a Los Angeles Project

Real week-by-week kitchen remodel timeline for a Los Angeles project. Design, permits, cabinets, demo, rough trades, and finish. What slips and why.

May 12, 20267 min readCSLB License #1072368
kitchen remodel timeline
Kitchen Remodeling project by MY Cali BUILDERS INC

Short answer. A typical Los Angeles kitchen remodel runs 4 to 6 months from signed contract to final inspection. Design and permits take 8 to 12 weeks. Cabinet fabrication runs 6 to 10 weeks in parallel. Active construction takes 8 to 10 weeks. The full week-by-week schedule below shows what happens and what tends to slip.

Almost every kitchen schedule overrun traces back to one of three problems: late selections, cabinet delivery surprises, or rough-trade conflicts uncovered after demo. The schedule below assumes selections are finalized by end of week 4 and the cabinets ordered immediately. Push selections later and every downstream phase slips.

Full week-by-week schedule

Phase 1: Design and selections

Weeks 1 to 4. Site measurement. Concept design. Cabinet layout and door style selection. Counter material selection. Appliance package finalized with model numbers. Plumbing and lighting selections. End of phase: signed-off drawings ready for permit submission and cabinet ordering.

Phase 2: Permit submission

Weeks 4 to 5. Submit to LADBS or local building department. Title 24 energy compliance documents prepared. Plan check typically begins inside 7 days of submission.

Phase 3: Cabinet fabrication and permit review

Weeks 5 to 14. Cabinets enter production. Plan check runs in parallel. Corrections resolved as needed. Permit issued by week 10 to 12. Cabinets delivered around week 12 to 14. Counter template not scheduled until cabinets are installed.

Phase 4: Demolition

Weeks 14 to 15. Existing kitchen removed. Floors protected. Appliances disconnected and stored. Containment dust barriers built. Hidden site conditions surface here (water damage, unpermitted prior work, undersized framing). Address before rough trades.

Phase 5: Rough trades

Weeks 15 to 17. Plumbing rough at new fixture locations. Electrical rough including new circuits for range, dishwasher, microwave, disposal, and under-cabinet lighting. HVAC adjustments if range hood vents through wall or roof. Rough inspection passed before drywall.

Phase 6: Drywall, paint, and tile

Weeks 17 to 19. Drywall hung and finished. Primer and first paint coat. Wall tile installed where applicable. Floors installed if not already in place.

Phase 7: Cabinet installation

Week 19. Cabinets set, leveled, and shimmed. Crown and toe kicks installed. Critical inspection week. Counter template scheduled after this is complete and accurate.

Phase 8: Counter template and fabrication

Weeks 19 to 21. Counter shop templates the cabinets in person. Fabrication runs 7 to 14 days. Sink and faucet selection finalized before template.

Phase 9: Counter install and final trades

Weeks 21 to 23. Counters set and seamed. Backsplash installed. Plumbing trim out. Electrical trim out. Appliance installation. Final paint touch-ups.

Phase 10: Punch list and final inspection

Weeks 23 to 24. Walkthrough. Punch list resolved. Final inspection scheduled with the building department. Final inspection passed. Project closed.

Where time gets lost

  • Cabinet selections decided after the contract signed. Adds 4 to 8 weeks.
  • Counter material picked after cabinets arrive. Adds 2 to 4 weeks.
  • Appliances not on site by cabinet install. Adds 1 to 3 weeks of trim work delay.
  • Permit corrections handled slowly. Each round adds 2 to 4 weeks.
  • Hidden water damage or knob-and-tube wiring discovered at demo. Adds 1 to 3 weeks.

For the price side, see kitchen remodel cost in Los Angeles. For cabinet selection, read custom kitchen cabinets in LA. For layout ideas, see small kitchen island ideas. For our build process, open the kitchen remodeling service page.

About the author

Written by the MY Cali BUILDERS INC team. Licensed California general contractor, CSLB #1072368. Based in Woodland Hills and serving the San Fernando Valley. About our team.

FAQs

Frequently asked questions

Plan 4 to 6 months from signed contract to final walkthrough. Design and permitting take 8 to 12 weeks. Cabinets take 6 to 10 weeks to fabricate. Active construction takes 4 to 8 weeks. The phases overlap by design but cabinet lead time sets the floor.
Cabinet lead time and permit approval. Together they account for 60 to 70 percent of the calendar. Construction itself is usually 4 to 8 weeks. Selecting cabinets and submitting permits in week one is the single highest-impact scheduling move.
Yes for most LA homeowners. Set up a temporary kitchenette with a microwave, kettle, and toaster oven in another room. Plan for the water shutoff to be intermittent during plumbing rough. Most clients leave town for the demo week.
The cabinet install week. If cabinets arrive damaged or short shipped, the entire downstream schedule (counters, backsplash, appliances) slips. Insist on a full delivery inspection on receipt.
Yes when applicable. Cosmetic refreshes without structural change can avoid plan check and start construction within 2 to 3 weeks. Layout changes or wall removals always require full plan check.
Keep reading

More from the blog

Ready to get started?

Get a free estimate

Free onsite visit. Written estimate. You will see the full scope before you decide. No pressure, no vague quotes.

License #1072368. Fully insured. Serving the San Fernando Valley since 2020.