# Kitchen Remodel Timeline: Week-by-Week Schedule for a Los Angeles Project

Real week-by-week kitchen remodel timeline for a Los Angeles project. Design, permits, cabinets, demo, rough trades, and finish. What slips and why.

May 12, 20267 min readCSLB License #1072368

![kitchen remodel timeline](https://www.mycalibuilders.com/blog-images/kitchen-remodel-timeline.jpeg)

Kitchen Remodeling project by MY Cali BUILDERS INC

**Short answer.** A typical Los Angeles kitchen remodel runs 4 to 6 months from signed contract to final inspection. Design and permits take 8 to 12 weeks. Cabinet fabrication runs 6 to 10 weeks in parallel. Active construction takes 8 to 10 weeks. The full week-by-week schedule below shows what happens and what tends to slip.

Almost every kitchen schedule overrun traces back to one of three problems: late selections, cabinet delivery surprises, or rough-trade conflicts uncovered after demo. The schedule below assumes selections are finalized by end of week 4 and the cabinets ordered immediately. Push selections later and every downstream phase slips.

## Full week-by-week schedule

### Phase 1: Design and selections

**Weeks 1 to 4.** Site measurement. Concept design. Cabinet layout and door style selection. Counter material selection. Appliance package finalized with model numbers. Plumbing and lighting selections. End of phase: signed-off drawings ready for permit submission and cabinet ordering.

### Phase 2: Permit submission

**Weeks 4 to 5.** Submit to LADBS or local building department. Title 24 energy compliance documents prepared. Plan check typically begins inside 7 days of submission.

### Phase 3: Cabinet fabrication and permit review

**Weeks 5 to 14.** Cabinets enter production. Plan check runs in parallel. Corrections resolved as needed. Permit issued by week 10 to 12. Cabinets delivered around week 12 to 14. Counter template not scheduled until cabinets are installed.

### Phase 4: Demolition

**Weeks 14 to 15.** Existing kitchen removed. Floors protected. Appliances disconnected and stored. Containment dust barriers built. Hidden site conditions surface here (water damage, unpermitted prior work, undersized framing). Address before rough trades.

### Phase 5: Rough trades

**Weeks 15 to 17.** Plumbing rough at new fixture locations. Electrical rough including new circuits for range, dishwasher, microwave, disposal, and under-cabinet lighting. HVAC adjustments if range hood vents through wall or roof. Rough inspection passed before drywall.

### Phase 6: Drywall, paint, and tile

**Weeks 17 to 19.** Drywall hung and finished. Primer and first paint coat. Wall tile installed where applicable. Floors installed if not already in place.

### Phase 7: Cabinet installation

**Week 19.** Cabinets set, leveled, and shimmed. Crown and toe kicks installed. Critical inspection week. Counter template scheduled after this is complete and accurate.

### Phase 8: Counter template and fabrication

**Weeks 19 to 21.** Counter shop templates the cabinets in person. Fabrication runs 7 to 14 days. Sink and faucet selection finalized before template.

### Phase 9: Counter install and final trades

**Weeks 21 to 23.** Counters set and seamed. Backsplash installed. Plumbing trim out. Electrical trim out. Appliance installation. Final paint touch-ups.

### Phase 10: Punch list and final inspection

**Weeks 23 to 24.** Walkthrough. Punch list resolved. Final inspection scheduled with the building department. Final inspection passed. Project closed.

## Where time gets lost

- Cabinet selections decided after the contract signed. Adds 4 to 8 weeks.
- Counter material picked after cabinets arrive. Adds 2 to 4 weeks.
- Appliances not on site by cabinet install. Adds 1 to 3 weeks of trim work delay.
- Permit corrections handled slowly. Each round adds 2 to 4 weeks.
- Hidden water damage or knob-and-tube wiring discovered at demo. Adds 1 to 3 weeks.

For the price side, see [kitchen remodel cost in Los Angeles](https://www.mycalibuilders.com/blog/kitchen-remodel-cost-los-angeles). For cabinet selection, read [custom kitchen cabinets in LA](https://www.mycalibuilders.com/blog/custom-kitchen-cabinets-los-angeles). For layout ideas, see [small kitchen island ideas](https://www.mycalibuilders.com/blog/small-kitchen-island-ideas). For our build process, open the [kitchen remodeling service page](https://www.mycalibuilders.com/services/kitchen-remodeling).

Free onsite estimate

### Ready to start your Kitchen Remodeling project?

We come to you, review the scope, and give you a written estimate before any work starts. No pressure. No vague quotes. CA Contractor License #1072368.

[Call us](tel:+13102200903) [Text Us](sms:+13102200903) [Get a free estimate](https://www.mycalibuilders.com/contact-us)

Project gallery

## Real projects from our crew

Recent work from MY Cali Builders across the San Fernando Valley.

[See full gallery](https://www.mycalibuilders.com/gallery)

![Traditional kitchen with wooden cabinets and tiled countertops.](https://www.mycalibuilders.com/project-media/kitchen-remodeling/WhatsApp%20Image%202026-05-08%20at%2008.35.33%20(4).jpeg)

Kitchen Remodeling

![Modern living space with wood paneling and minimalist furniture.](https://www.mycalibuilders.com/project-media/kitchen-remodeling/WhatsApp%20Image%202026-05-08%20at%2008.35.34%20(1).jpeg)

Kitchen Remodeling

![Contemporary kitchen featuring stainless steel appliances and patterned backsplash.](https://www.mycalibuilders.com/project-media/kitchen-remodeling/WhatsApp%20Image%202026-05-08%20at%2008.35.43%20(1).jpeg)

Kitchen Remodeling

Related services

### See how we approach this work

- [Kitchen Remodeling](https://www.mycalibuilders.com/services/kitchen-remodeling)
- [Kitchen Remodeling in San Fernando Valley](https://www.mycalibuilders.com/service-areas/san-fernando-valley/kitchen-remodeling)
- [Kitchen Remodeling in Calabasas](https://www.mycalibuilders.com/service-areas/calabasas/kitchen-remodeling)

About the author

Written by the MY Cali BUILDERS INC team. Licensed California general contractor, CSLB #1072368. Based in Woodland Hills and serving the San Fernando Valley. [About our team](https://www.mycalibuilders.com/about-us).

FAQs

## Frequently asked questions

Plan 4 to 6 months from signed contract to final walkthrough. Design and permitting take 8 to 12 weeks. Cabinets take 6 to 10 weeks to fabricate. Active construction takes 4 to 8 weeks. The phases overlap by design but cabinet lead time sets the floor.

Cabinet lead time and permit approval. Together they account for 60 to 70 percent of the calendar. Construction itself is usually 4 to 8 weeks. Selecting cabinets and submitting permits in week one is the single highest-impact scheduling move.

Yes for most LA homeowners. Set up a temporary kitchenette with a microwave, kettle, and toaster oven in another room. Plan for the water shutoff to be intermittent during plumbing rough. Most clients leave town for the demo week.

The cabinet install week. If cabinets arrive damaged or short shipped, the entire downstream schedule (counters, backsplash, appliances) slips. Insist on a full delivery inspection on receipt.

Yes when applicable. Cosmetic refreshes without structural change can avoid plan check and start construction within 2 to 3 weeks. Layout changes or wall removals always require full plan check.

Keep reading

## More from the blog

[![kitchen remodel cost los angeles](https://www.mycalibuilders.com/blog-images/kitchen-remodel-cost-los-angeles.jpeg)](https://www.mycalibuilders.com/blog/kitchen-remodel-cost-los-angeles)

Kitchen Remodeling10 min read

### [Kitchen Remodel Cost in Los Angeles: Budget, Mid-Range, and Luxury Tiers](https://www.mycalibuilders.com/blog/kitchen-remodel-cost-los-angeles)

What a kitchen remodel actually costs in Los Angeles in 2026. Budget, mid-range, and luxury price tiers with line item breakdowns for cabinets and labor.

May 12, 2026 [Read article](https://www.mycalibuilders.com/blog/kitchen-remodel-cost-los-angeles)

[![small kitchen island ideas](https://www.mycalibuilders.com/blog-images/small-kitchen-island-ideas.jpeg)](https://www.mycalibuilders.com/blog/small-kitchen-island-ideas)

Kitchen Remodeling9 min read

### [Small Kitchen Island Ideas: 12 Layouts That Work in Compact LA Kitchens](https://www.mycalibuilders.com/blog/small-kitchen-island-ideas)

12 small kitchen island ideas with real dimensions, seating tips, storage tricks, and clearance rules. Made for compact Los Angeles kitchens.

May 12, 2026 [Read article](https://www.mycalibuilders.com/blog/small-kitchen-island-ideas)

[![custom kitchen cabinets los angeles](https://www.mycalibuilders.com/blog-images/custom-kitchen-cabinets-los-angeles.jpeg)](https://www.mycalibuilders.com/blog/custom-kitchen-cabinets-los-angeles)

Kitchen Remodeling9 min read

### [Custom Kitchen Cabinets in Los Angeles: Stock vs Semi-Custom vs Custom](https://www.mycalibuilders.com/blog/custom-kitchen-cabinets-los-angeles)

Custom kitchen cabinets in Los Angeles compared with stock and semi-custom. Real 2026 prices per linear foot, lead times, and material grades.

May 12, 2026 [Read article](https://www.mycalibuilders.com/blog/custom-kitchen-cabinets-los-angeles)

[See all articles](https://www.mycalibuilders.com/blog)

Ready to get started?

## Get a free estimate

Free onsite visit. Written estimate. You will see the full scope before you decide. No pressure, no vague quotes.

[Call us](tel:+13102200903) [Text Us](sms:+13102200903) Send us a message

License #1072368. Fully insured. Serving the San Fernando Valley since 2020.