How Long Does It Take to Remodel a House in Los Angeles?

Realistic timelines for whole house, kitchen, bathroom, and ADU remodels in Los Angeles. Design, permits, construction, and where projects slip.

May 12, 20266 min readCSLB License #1072368
how long does it take to remodel a house
Trust and Process project by MY Cali BUILDERS INC

Short answer. A whole-house remodel in Los Angeles takes 7 to 12 months from contract to close. A kitchen runs 3 to 5 months. A bathroom runs 3 to 5 months. ADUs run 6 to 12 months. Design and permits often take longer than construction itself.

Typical timelines by project type

Project typeDesign and permitsConstructionTotal
Bathroom remodel4 to 8 weeks4 to 7 weeks3 to 5 months
Kitchen remodel4 to 8 weeks6 to 10 weeks3 to 5 months
ADU (detached)10 to 16 weeks16 to 26 weeks6 to 12 months
Garage conversion ADU8 to 12 weeks10 to 16 weeks5 to 7 months
Whole house remodel12 to 20 weeks16 to 28 weeks7 to 12 months
Whole house + addition16 to 28 weeks24 to 40 weeks10 to 17 months

Where time goes

Design and selections

Floor plans, elevations, finish selections, fixture selections, lighting design, and structural review. Plan 4 to 16 weeks. Faster when the homeowner is decisive and has reference images ready.

Permits

LADBS plan check ranges 2 to 16 weeks depending on project complexity. Coastal Commission overlays, HPOZ review, and hillside grading reviews each add 1 to 4 months. Title 24 energy compliance review runs in parallel.

Material lead time

Cabinets: 6 to 12 weeks. Tile: 2 to 6 weeks. Windows: 6 to 14 weeks. Plumbing fixtures: 2 to 8 weeks. Major appliances: 3 to 12 weeks. Order long-lead items first.

Construction

Demo through final inspection. Schedule depends on permit type, scope, and trade coordination. A reasonable benchmark is one week per $20,000 to $30,000 of construction cost on residential remodel work.

Three common reasons projects slip

  1. Late material delivery. Cabinets and tile arrive late or damaged. Mitigated by ordering early and inspecting on arrival.
  2. Mid-project change orders. The homeowner changes scope after demo. Each change adds 1 to 3 weeks.
  3. Plan check correction rounds. Each round adds 1 to 3 weeks. Quality drawings reduce correction rounds.

For project-specific timelines, read kitchen remodel timeline and bathroom remodel timeline. For survival strategies during construction, see how to survive a home renovation.

About the author

Written by the MY Cali BUILDERS INC team. Licensed California general contractor, CSLB #1072368. Based in Woodland Hills and serving the San Fernando Valley. About our team.

FAQs

Frequently asked questions

Plan 7 to 12 months from signed contract to final inspection. Design and permits: 3 to 5 months. Construction: 4 to 7 months. Whole-house projects with structural changes can run 12 to 18 months.
Plan 3 to 5 months total. Design and permits: 4 to 8 weeks. Construction: 6 to 10 weeks. See the dedicated kitchen remodel timeline post for the week-by-week schedule.
LADBS plan check runs 2 to 8 weeks for typical remodels and 8 to 16 weeks for additions with structural review. Coastal Commission or HPOZ overlays add 2 to 4 months.
Sometimes. Bathroom-only remodels with no permit can wrap in 4 to 6 weeks. Express plan check at LADBS shaves 2 to 3 weeks. Pre-ordered materials and finalized selections shave 3 to 6 weeks.
Three causes account for most slips: late material delivery, mid-project change orders, and plan check correction rounds. All three are largely controllable with disciplined planning.
Keep reading

More from the blog

Ready to get started?

Get a free estimate

Free onsite visit. Written estimate. You will see the full scope before you decide. No pressure, no vague quotes.

License #1072368. Fully insured. Serving the San Fernando Valley since 2020.