Bathroom Remodel Timeline: Week-by-Week Schedule

Week-by-week bathroom remodel timeline for a Los Angeles project. Design, permits, demo, rough trades, tile, and finish. What slips and why.

May 12, 20266 min readCSLB License #1072368
bathroom remodel timeline
Bathroom Remodeling project by MY Cali BUILDERS INC

Short answer. A typical Los Angeles bathroom remodel runs 3 to 5 months from signed contract to final inspection. Design and permits take 4 to 8 weeks. Active construction takes 4 to 7 weeks. The full week-by-week schedule is below.

Week-by-week schedule

Phase 1: Design and selections

Weeks 1 to 3. Site measurement. Layout decisions. Tile, vanity, fixture, and lighting selections. End of phase: signed-off drawings and complete material list ready for ordering.

Phase 2: Permit submission and material ordering

Weeks 3 to 4. Submit to LADBS. Order all tile, vanity, fixtures, glass enclosure, and lighting. Long-lead items confirmed with delivery dates.

Phase 3: Permit and material lead time

Weeks 4 to 10. Plan check runs 2 to 6 weeks. Tile and vanity lead times run 3 to 8 weeks. Materials and permits both ready by week 10 in typical projects.

Phase 4: Demolition

Week 11. Existing fixtures, tile, drywall, and flooring removed. Floor and wall conditions inspected. Hidden water damage and prior unpermitted plumbing surface here.

Phase 5: Plumbing rough

Weeks 11 to 12. New supply lines and drain locations roughed in. Shower valve set. Tub or shower base set. Rough plumbing inspection passed.

Phase 6: Electrical rough

Week 12. New circuits run. Vanity lights, fan, and accent lighting roughed in. Rough electrical inspection passed.

Phase 7: Waterproofing and framing closures

Weeks 12 to 13. Shower walls and floor waterproofed with a code-approved system. Framing closures complete. Drywall hung outside the shower.

Phase 8: Tile installation

Weeks 13 to 15. Wall tile, floor tile, niche, and bench tile installed. Grout applied. Sealing where required by material.

Phase 9: Vanity, plumbing trim, and electrical trim

Week 15. Vanity set. Counter installed. Faucet, toilet, shower trim, and tub spout installed. Light fixtures, switches, and outlets installed.

Phase 10: Shower glass template and install

Weeks 15 to 17. Glass shop templates after tile is complete. Fabrication runs 5 to 10 days. Glass installed and silicone cured.

Phase 11: Punch list and final inspection

Week 17. Walkthrough. Punch list resolved. Final inspection with the building department. Project closed.

Where the schedule slips

  • Tile arriving short shipped or damaged. Plan to receive and inspect tile two weeks before install.
  • Vanity backorders. Lead times stretched to 8 plus weeks on popular brands. Order in week 1.
  • Plan check corrections. Each correction round adds 1 to 3 weeks.
  • Hidden water damage from prior leaks. Adds 1 to 2 weeks at the rough phase.

For pricing, read bathroom remodel cost in Los Angeles. For layouts, read small bathroom remodel ideas. For walk-in showers, see walk-in shower remodels. To start, open the contact page.

About the author

Written by the MY Cali BUILDERS INC team. Licensed California general contractor, CSLB #1072368. Based in Woodland Hills and serving the San Fernando Valley. About our team.

FAQs

Frequently asked questions

Plan 3 to 5 months from contract to final inspection. Design and permits take 4 to 8 weeks. Construction takes 4 to 7 weeks. The largest variables are tile lead time, vanity lead time, and how quickly selections are finalized.
Tile installation is the longest single phase, typically 7 to 14 days for a full bathroom. Wall tile, floor tile, niche, and bench all require careful sequencing and dry time between steps.
No. The bathroom is fully out of service for 4 to 7 weeks during construction. Plan to use another bathroom or set up a temporary arrangement in a powder room.
LADBS plan check for bathroom remodels typically runs 2 to 6 weeks. Like-for-like fixture replacements in the same location may not require permits. Layout changes always require plan check.
Tile delivery week. Specialty tile from a single supplier often arrives short shipped or damaged. The downstream schedule (waterproofing, install, grout, glass template) all wait for complete tile on site.
Keep reading

More from the blog

Ready to get started?

Get a free estimate

Free onsite visit. Written estimate. You will see the full scope before you decide. No pressure, no vague quotes.

License #1072368. Fully insured. Serving the San Fernando Valley since 2020.